• Tuesday, 15 November 2022

    Energean sees case for more EastMed gas investment

    London headquartered exploration and production outfit Energean is banging the drum for more EastMed gas investment: The start of drilling at Israel’s Karish gas field following an agreement over disputed maritime territory between Israel and Lebanon should pave the way...
  • Sunday, 28 August 2022

    South Korea signs USD 2.2 bn contract with Rosatom for Dabaa nuclear plant

    South Korea is getting in on Dabaa: South Korea’s state nuclear power company has signed a KRW 3 tn (USD 2.2 bn) contract with Rosatom to supply equipment and help build the 4.8 GW Dabaa nuclear plant, the companies said...
  • Thursday, 21 July 2022

    Rosatom starts construction of Dabaa nuclear plant

    The Dabaa nuclear plant is finally getting off the ground: Russian state nuclear company Rosatom has started building the 4.8 GW Dabaa nuclear power plant, the company said in a statement. The company yesterday began laying the concrete foundations for...
  • Sunday, 3 July 2022

    Rosatom secures permit to start building Dabaa nuclear plant

    Dabaa gets the regulatory thumbs-up: Russian state nuclear company Rosatom has received a permit from our nuclear authority to begin building the 4.8 GW Dabaa nuclear power plant, a statement by Rosatom read.Next step: construction. The permit “[paves] the way...
  • Sunday, 5 June 2022

    Russia’s Rosatom forges ahead with equipment for Dabaa nuclear plant

    One step closer to the ​​Dabaa nuclear plant: Russian state nuclear company Rosatom has started manufacturing equipment for the 4.8 GW Dabaa nuclear power plant, it said in a statement. Rosatom said in January that it expects to be able...
  • Wednesday, 19 January 2022

    Rosatom on track to break ground on Dabaa in July

    Construction on the Dabaa nuclear power plant is on track to begin “this summer, tentatively in July,” the director of Russia’s state-owned Rosatom, General Alexey Likhachev, told TASS. The timeline matches what we were told by Egyptian Nuclear and Radiological...
  • Wednesday, 14 July 2021

    Dabaa delayed

    Dabaa delayed by two years, thanks to covid: The Dabaa nuclear plant will likely be finished two years later than planned due to disruption caused by the covid-19 pandemic, the spokesperson for Egypt’s nuclear regulator told Enterprise yesterday. Work on...
  • Tuesday, 13 July 2021

    Rubles for Dabaa contractors

    Rosatom will provide between USD 3-4 bn to several Egyptian contractors working at the site of the Dabaa nuclear power plant as soon as permits are issued and construction begins, the company’s Chief Sustainability Officer Polina Lion told a presser...
  • Tuesday, 6 July 2021

    Egypt applies for construction permits for Dabaa nuclear plant

    Egypt applies for construction permits for Dabaa nuclear plant: Egypt's Nuclear Power Plants Authority has submitted licensing documentation for the first two units of Dabaa nuclear power plant to regulators in what should be the final bureaucratic hurdle to clear...

Enterprise is a daily publication of Enterprise Ventures LLC, an Egyptian limited liability company (commercial register 83594), and a subsidiary of Inktank Communications. Summaries are intended for guidance only and are provided on an as-is basis; kindly refer to the source article in its original language prior to undertaking any action. Neither Enterprise Ventures nor its staff assume any responsibility or liability for the accuracy of the information contained in this publication, whether in the form of summaries or analysis. © 2022 Enterprise Ventures LLC.

Enterprise is available without charge thanks to the generous support of HSBC Egypt (tax ID: 204-901-715), the leading corporate and retail lender in Egypt; EFG Hermes (tax ID: 200-178-385), the leading financial services corporation in frontier emerging markets; SODIC (tax ID: 212-168-002), a leading Egyptian real estate developer; SomaBay (tax ID: 204-903-300), our Red Sea holiday partner; Infinity (tax ID: 474-939-359), the ultimate way to power cities, industries, and homes directly from nature right here in Egypt; CIRA (tax ID: 200-069-608), the leading providers of K-12 and higher level education in Egypt; Orascom Construction (tax ID: 229-988-806), the leading construction and engineering company building infrastructure in Egypt and abroad; Moharram & Partners (tax ID: 616-112-459), the leading public policy and government affairs partner; Palm Hills Developments (tax ID: 432-737-014), a leading developer of commercial and residential properties; Mashreq (tax ID: 204-898-862), the MENA region’s leading homegrown personal and digital bank; Industrial Development Group (IDG) (tax ID:266-965-253), the leading builder of industrial parks in Egypt; Hassan Allam Properties (tax ID:  553-096-567), one of Egypt’s most prominent and leading builders; and Saleh, Barsoum & Abdel Aziz (tax ID: 220-002-827), the leading audit, tax and accounting firm in Egypt.