Ethiopia’s PM seems to be giving assurances that early GERD filling is harmless

Ethiopia is trying to reassure Egypt, Sudan that early filling of GERD is harmless: The first phase of filling the Grand Ethiopian Renaissance Dam (GERD) will not hurt the Nile’s downstream countries, Egypt and Sudan, Ethiopian Prime Minister Abiy Ahmed said in a statement aired on Ethiopian state TV on Wednesday, as the countries prepare to return to the negotiating table. Addis Ababa last week announced that it had finished the first stage of filling the reservoir after the three countries agreed to restart talks in search of an elusive agreement on filling and operating the dam. “We have successfully completed the first dam filling without bothering and hurting anyone else. Now the dam is overflowing downstream,” Ahmed said. This “has shown to the rest of the world that our country could stand firm with its two legs from now onwards.”

Egypt maintains that downstream water flow will be interrupted: The early filling has already led to a shortage of water in Sudanese silos and means that Egypt will be receiving its share of the Nile annual flood as late as mid-August every year, Masrawy reports, quoting an Irrigation Ministry official with knowledge of the GERD negotiations. Egypt had previously been receiving its share at the end of July.

The dam is now on track to reach full energy generation capacity by 2023, but “now we have to finish the remaining construction and diplomatic issues,” the Ethiopian statement said. Electricity generation could start as early as January or February 2021, and the “the historic achievement of the first stage of filling … is a testament to the end of the unfair use of the Nile,” Ethiopian Deputy PM Demeke Mekonnen said.

Egypt not looking for open conflict –El Sisi: President Abdel Fattah El Sisi indirectly addressed the GERD impasse in his 23 July speech, saying that, while Egypt actively avoids conflict, it “is able, when needed, to take the necessary measures to protect its historical rights and gains” (watch, runtime: 7:08).

The White House is reportedly lining up sanctions on Ethiopia if the negotiations fail to yield a mutually satisfactory agreement, a Foreign Policy piece quoting six unnamed American officials and congressional aides suggests. This could mean withholding unspecified aid the US provides to the African nation. Washington-mediated talks that wrapped up earlier this year failed to convince Ethiopia to sign a final agreement, and while formal statements coming out of Trump administration officials assert the US was and continues to be “an impartial mediator,” Foreign Policy suggests that “there’s growing concern that the Trump administration is putting its thumb on the scales to favor Egypt at the expense of Ethiopia.”

Background: El Sisi, Ahmed, and Sudanese PM Abdalla Hamdok agreed at an African Union (AU) sponsored summit last week to continue to strive toward a legally binding agreement over the filling of the dam’s reservoir, rules to operate the dam, and future developments in the Blue Nile. The dam is expected to take between 5-7 years to fill although the exact timeline for this remains one of the key points of disagreement between the three countries. The AU was also out with a statement over the weekend recapping the summit, which was hosted by current AU head and South African President Cyril Ramaphosa.

The story is still getting attention in the foreign press: Bloomberg | The National.

Enterprise is a daily publication of Enterprise Ventures LLC, an Egyptian limited liability company (commercial register 83594), and a subsidiary of Inktank Communications. Summaries are intended for guidance only and are provided on an as-is basis; kindly refer to the source article in its original language prior to undertaking any action. Neither Enterprise Ventures nor its staff assume any responsibility or liability for the accuracy of the information contained in this publication, whether in the form of summaries or analysis. © 2022 Enterprise Ventures LLC.

Enterprise is available without charge thanks to the generous support of HSBC Egypt (tax ID: 204-901-715), the leading corporate and retail lender in Egypt; EFG Hermes (tax ID: 200-178-385), the leading financial services corporation in frontier emerging markets; SODIC (tax ID: 212-168-002), a leading Egyptian real estate developer; SomaBay (tax ID: 204-903-300), our Red Sea holiday partner; Infinity (tax ID: 474-939-359), the ultimate way to power cities, industries, and homes directly from nature right here in Egypt; CIRA (tax ID: 200-069-608), the leading providers of K-12 and higher level education in Egypt; Orascom Construction (tax ID: 229-988-806), the leading construction and engineering company building infrastructure in Egypt and abroad; Moharram & Partners (tax ID: 616-112-459), the leading public policy and government affairs partner; Palm Hills Developments (tax ID: 432-737-014), a leading developer of commercial and residential properties; Mashreq (tax ID: 204-898-862), the MENA region’s leading homegrown personal and digital bank; Industrial Development Group (IDG) (tax ID:266-965-253), the leading builder of industrial parks in Egypt; Hassan Allam Properties (tax ID:  553-096-567), one of Egypt’s most prominent and leading builders; and Saleh, Barsoum & Abdel Aziz (tax ID: 220-002-827), the leading audit, tax and accounting firm in Egypt.